Counter-drone RF: the safety case is now the critical path
A US interagency memorandum routes every counter-drone system through FAA review, and NATO now sells 16 systems from a catalogue. Neither sets emission limits, so documented RF behaviour decides how fast jammers reach the field.
Counter-drone RF is moving from exception to procurement line
Two decisions in one week have changed how counter-drone radio-frequency systems reach the field. On 9 November five US departments announced a memorandum of understanding that routes every proposed counter-drone system through an FAA safety review before deployment [1]. Four days earlier NATO opened a counter-drone marketplace from which Allies can order 16 pre-selected solutions without a further tender [11]. Neither document publishes a single emission limit. Both assume that the spectrum and aviation-safety case will be made somewhere else. For operators and integrators, that somewhere is now the critical path.
The US memorandum sits on top of a regulatory stack built since July. It does not expand legal authority or add funding [4]. Its value is process. The gap it closes is the one between permission to jam and permission to jam near aircraft.
What the documents say
The FAA release names the Departments of Transportation, War, Homeland Security, Energy and Justice, with the effort led by the White House Task Force to Restore American Airspace Sovereignty [1]. Partners will work with the FAA and the FCC on systems that detect, track, stop or take control of drones, and will consider DOT, FAA and FCC requirements and test data throughout development and evaluation [1]. The FAA will run safety risk assessments and may impose its own measures, including airspace restrictions [1][3]. The text of the memorandum has not been published [3][5].
Sources differ on who is party. The FAA lists five departments [1]. Reuters lists Transportation, the Pentagon, Energy and Justice, without Homeland Security [2]. DroneXL lists the FAA itself as a party alongside DHS and the four others [5]. Until the text appears, the signatory list should be treated as unconfirmed.
Throughput is the headline operational figure. An FAA official told Reuters the agency has approved more than 1,000 counter-drone coordinations with the Pentagon and DHS and can turn the process around in 24 hours [2]. DroneLife reports that previously evaluated systems may get shorter reviews [4]. The figures on threat volume diverge because they measure different things: Reuters cites Pentagon figures of more than 1,000 drone incursions along the southern border each month [2], while DroneXL cites more than 300 border drone defeats this year, only two publicly identified [5].
The trigger for all this was not a jammer but a laser. In February the FAA closed El Paso airspace after Customs and Border Protection used a Pentagon laser system without a completed FAA review. Reuters reports the order was set for 10 days and lifted after about eight hours [2]. A second engagement near Fort Hancock destroyed a CBP drone [2][5]; DroneXL counts 14 cancelled flights across the two closures [5]. The FAA completed a safety assessment of that laser on 10 April [6].
The RF layer underneath
The spectrum rules that matter for jammers and takeover systems were set in July. Under the SAFER SKIES Act and a DOJ/DHS interim final rule, qualifying state, local, tribal and territorial agencies may mitigate drones, including by transmitting RF, but only with certified personnel and systems on the Authorized Technologies List or Authorized Systems List [9]. The FCC issued a 180-day nationwide special temporary authority for those agencies and waived equipment-authorisation rules for listed systems [9].
Two FCC declaratory rulings define the legal edges. DA 26-655 holds that Section 333, the ban on wilful interference, does not apply to federal C-UAS use, and extends derivative immunity to contractors who meet the NTIA Manual’s federal-station tests and to certified local agencies using listed equipment [8]. Local agencies must notify the Attorney General and DHS within 48 hours of any mitigation action, including jamming [8]. DA 26-654 lets non-federal developers jam their own drone links under an experimental authorisation, provided the same entity controls both ends and no harmful interference reaches other stations. GNSS jamming is excluded [7].
The mobile industry is not satisfied. CTIA filed four petitions for reconsideration in August, asking for notice to, coordination with or approval from affected licensees, and for stronger interference guardrails [9]. We could not retrieve a later FCC order on those petitions.
Inside the Department of War, an October memorandum named spectrum certification and frequency access among four approval barriers, barred repeat weapons-safety reviews for unchanged systems and set a 30-day escalation rule [14]. Its December 2025 homeland C-UAS policy left engagement criteria deliberately non-prescriptive and made all mitigation systems available for consideration [15].
NATO buys from a catalogue
NATO’s marketplace, run by the NCIA, offers 16 solutions from Alta Ares, Axon Enterprise, Northrop Grumman, OSL UK and Quantum Systems [11]. Every one has already been deployed in Allied countries and in Ukraine [11]. The framework contracts run for 18 months, with €3.1 million set aside for further testing [11][12]. They are not purchase orders; spending happens through later task orders [12][13].
Bids were scored against point, area (up to 3 km), border (20 km) and convoy scenarios [12][13]. NATO has not published the lot split, so which lots involve RF detection or RF defeat is not public; Alta Ares claims six [13]. Accounts of the timeline differ. AeroTime reports the October 2025 notice anticipated awards by 30 January 2026 on a one-year term [12]. DroneXL reports a planned award date of 30 June [13]. Both agree the award slipped to 5 November.
What it means for practitioners
Procurement speed is no longer the binding constraint. Certification is. A US agency can buy mitigation equipment with grant money before it may legally operate it. The FY2027 C-UAS grant guidance states that authority to purchase is not authority to operate, and requires ATL or ASL listing plus training and accreditation before use [10]. The $250 million round closes on 16 November [10][5].
The second consequence is evidential. The FAA review, the FCC experimental route and the derivative-immunity tests all depend on documented RF behaviour: what the system radiates, where, and who controls it [1][7][8]. Vendors that cannot produce that record will lose time at the FAA desk rather than at contract award.
- Treat a measured emissions profile, including out-of-band and harmonic behaviour, as a deliverable alongside the system. It feeds the FAA safety case and FCC coordination [1][7].
- Confirm which instrument authorises each transmission: federal exemption, derivative immunity, the special temporary authority, or an experimental licence. Each has different conditions [7][8][9].
- Track the expiry of the 180-day STA issued on 2 July and plan for its renewal or replacement [9].
- Build the 48-hour mitigation notification into operating procedures, not after-action reporting [8].
- Do not plan GNSS denial as a C-UAS test effect under the experimental ruling; it is excluded [7].
- For NATO buyers, ask suppliers for the deployment evidence that qualified them and for host-nation spectrum clearance status, since the catalogue does not grant frequency access [11][13].
Domain view
Counter-drone RF has reached the point every electronic attack capability reaches in peacetime airspace. The effector works. The question is whether its emissions can be shown not to harm the systems around it. The US has now built a review queue for that question, and NATO has built a shopping list that assumes nations will answer it. For ELINT and spectrum teams, the work is characterisation and deconfliction before deployment, not after an airport closes.
Sources
Every R3KONX article cites its primary material. 15 sources, in order of first citation. Links open the original publication.
- Trump Administration Deepens Interagency Collaboration to Protect the Nation's Skies From Unmanned Threats Federal Aviation Administration · 2026-11-09
- US vows to speed up deployment of counter-drone systems to address threats (Reuters, syndicated) Reuters via KFGO · 2026-11-09
- Agencies agree to counter unauthorized drones without compromising civilian safety under new MOU DefenseScoop · 2026-11-09
- Federal Agreement Could Cut Counter-Drone Reviews to 24 Hours DroneLife · 2026-11-09
- DHS Pact Gives FAA Counter-Drone Review as Hegseth Calls Lasers Safe DroneXL · 2026-11-09
- FAA and DOW Sign Landmark Safety Agreement to Protect Southern Border Federal Aviation Administration · 2026-04-10
- Declaratory Ruling DA 26-654: Application of Section 333 to the Testing of Counter-UAS Technologies Federal Communications Commission · 2026-07-02
- Declaratory Ruling DA 26-655: Section 333 and federal counter-UAS use Federal Communications Commission · 2026-07-02
- Federal Agencies Establish Framework for State, Local Counter-Drone Operations Davis Wright Tremaine (Broadband Advisor) · 2026-07
- Counter-UAS funding goes nationwide: Key takeaways from FEMA's FY 2027 C-UAS Grant Program Hogan Lovells Cadwalader · 2026-11-04
- NATO accelerates procurement for counter-drone technologies NATO · 2026-11-05
- NATO opens counter-drone marketplace with 16 systems from five companies AeroTime · 2026-11-06
- NATO Counter-Drone Catalog: 2024 Startup Says It Won 6 of 16 Lots DroneXL · 2026-11-09
- U.S. Department of War orders faster counter-drone approvals with 30-day escalation rule and limits on repeat safety reviews Defence Industry Europe · 2026-10-02
- Fact Sheet: C-UAS Policy in the U.S. Homeland U.S. Department of War · 2026-02-10
Researched and written by the R3KONX Analysis Desk from the primary material cited below. The US memorandum text and NATO's lot breakdown are unpublished, so details of both rest on official releases and trade reporting that differ in places. Corrections: event@r3konx.asia.